Renewable energy in Serbia

Serbia has 1.8 GW of operating renewable capacity in the data, across 55 plants. Hydropower is the largest source at 944 MW (53% of the total). That is 23% of the 7.8 GW of operating power capacity of all kinds that the same tracker lists for Serbia (share of capacity in this dataset, not of national electricity generation). Plants that started operating from 2015 to 2025 add up to 811 MW, which is 45% of today's operating renewable capacity. A further 66 MW is under construction and 10.9 GW is announced or in pre-construction.

Operating
1.8 GW55 plants
Share of capacity in this dataset
23%of 7.8 GW operating, all kinds
Started 2015 to 2025
811 MWoperating plants
Pipeline
11.0 GW66 MW building, 10.9 GW announced

Capacity by technology

Renewable capacity in Serbia by technology, operating and pipeline. Announced includes pre-construction.
TechnologyOperatingPlantsShareUnder constructionAnnounced
Solar PV199 MW3711%04.1 GW
Onshore wind604 MW834%66 MW6.8 GW
Hydropower944 MW753%00
Bioenergy37 MW32.1%00
All renewables1.8 GW55100%66 MW10.9 GW

Of the operating solar, 172 MW comes from TransitionZero Solar Asset Mapper records (CC BY-NC 4.0, non-commercial reuse only). The open data files list that part separately.

The build-out by year

0 MW250 MW500 MW19901995200020052010201520202025
Solar PVOnshore windHydropowerBioenergy
Show the figures as a table
Operating renewable capacity in Serbia by the year it started, 1990 to 2025
YearStarted operatingSolar PVConcentrated solarOnshore windOffshore windHydropowerGeothermalBioenergyWind (type not stated)
199080 MW000080 MW000
200920 MW0020 MW00000
201714 MW12 MW000002 MW0
201857 MW11 MW042 MW0005 MW0
2019336 MW4 MW0332 MW00000
20211 MW1 MW0000000
20225 MW5 MW0000000
202373 MW43 MW0000030 MW0
2024265 MW65 MW0200 MW00000
202560 MW60 MW0000000

Capacity of today's operating plants, by the year the plant started. Plants since retired are not in the data. 10 MW of operating capacity has no recorded start year and is left out of this chart. Earlier years and 2026 (a partial year) are in the data but outside the chart; the biggest year is 1966 with 420 MW.

Largest renewable plants in Serbia

The ten largest operating renewable plants in Serbia.
#PlantTechnologyCapacityStatusStarted
1Bajina Bašta hydroelectric plantHydropower420 MWOperating1966
2Cibuk wind farmOnshore wind158 MWOperating2019
3Vlasina hydroelectric plantHydropower129 MWOperating1955
4Zvornik hydroelectric plantHydropower126 MWOperating1955
5Krivača wind farmOnshore wind106 MWOperating2024
6Kovacica wind farmOnshore wind105 MWOperating2019
7Bistrica Eps hydroelectric plantHydropower102 MWOperating1959
8Pupin wind farmOnshore wind95 MWOperating2024
9Pirot hydroelectric plantHydropower80 MWOperating1990
10Kosava wind farmOnshore wind69 MWOperating2019

Largest in the pipeline

The five largest renewable projects under construction or announced in Serbia.
#PlantTechnologyCapacityStatusStarted
1Bor wind farmOnshore wind1.5 GWAnnouncednot recorded
2Stiško Polje wind farmOnshore wind1.0 GWAnnouncednot recorded
3Samos wind farmOnshore wind888 MWAnnouncednot recorded
4Kula solar farmSolar PV660 MWAnnounced2026
5Banat wind farmOnshore wind563 MWAnnounced2027

Questions

How much renewable energy capacity does Serbia have?

Serbia has 1.8 GW of operating renewable capacity across 55 plants in the Global Energy Monitor data (solar, wind, hydropower, geothermal and bioenergy).

What is the biggest source of renewable capacity in Serbia?

Hydropower, with 944 MW operating, which is 53% of Serbia's operating renewable capacity in the data.

What share of Serbia's power capacity is renewable?

23% of the operating capacity in this dataset (1.8 GW of 7.8 GW). This is a share of plant capacity listed by Global Energy Monitor, which tracks larger plants, not a share of the electricity actually generated or of national grid statistics.

How fast is Serbia building renewables?

Operating plants that started from 2015 to 2025 total 811 MW, and the biggest single year in the data is 1966 with 420 MW. Plants with no recorded start year are not counted in the build-out by year.

What is the largest renewable plant in Serbia?

Bajina Bašta hydroelectric plant, a hydropower plant of 420 MW, which started operating in 1966.

How much renewable capacity is being built or planned in Serbia?

66 MW is under construction and 10.9 GW is announced or in pre-construction. Some announced projects will never be built.

Where does this data come from?

Global Energy Monitor, Global Integrated Power Tracker, September 2026 (Global Energy Monitor, Global Integrated Power Tracker, V2). Licensed CC BY 4.0, with some solar records CC BY-NC 4.0. Figures are as recorded by Global Energy Monitor and are not independently confirmed.

Data as of September 2026 (Global Energy Monitor, Global Integrated Power Tracker, V2). Status counted: operating, under construction, and announced (including pre-construction). Retired, shelved, cancelled and mothballed plants are left out. Missing values are shown as missing. Method.