Renewable energy in Tanzania
Tanzania has 2.9 GW of operating renewable capacity in the data, across 15 plants. Hydropower is the largest source at 2.7 GW (93% of the total). That is 78% of the 3.8 GW of operating power capacity of all kinds that the same tracker lists for Tanzania (share of capacity in this dataset, not of national electricity generation). Plants that started operating from 2015 to 2025 add up to 2.4 GW, which is 80% of today's operating renewable capacity. A further 168 MW is under construction and 5.3 GW is announced or in pre-construction.
- Operating
- 2.9 GW15 plants
- Share of capacity in this dataset
- 78%of 3.8 GW operating, all kinds
- Started 2015 to 2025
- 2.4 GWoperating plants
- Pipeline
- 5.4 GW168 MW building, 5.3 GW announced
Capacity by technology
| Technology | Operating | Plants | Share | Under construction | Announced |
|---|---|---|---|---|---|
| Solar PV | 159 MW | 3 | 5.4% | 50 MW | 2.1 GW |
| Onshore wind | 0 | 0 | 0.0% | 0 | 1.3 GW |
| Offshore wind | 0 | 0 | 0.0% | 0 | 450 MW |
| Hydropower | 2.7 GW | 6 | 93% | 88 MW | 929 MW |
| Geothermal | 0 | 0 | 0.0% | 30 MW | 203 MW |
| Bioenergy | 46 MW | 6 | 1.6% | 0 | 21 MW |
| Wind (type not stated) | 0 | 0 | 0.0% | 0 | 320 MW |
| All renewables | 2.9 GW | 15 | 100% | 168 MW | 5.3 GW |
Of the operating solar, 9 MW comes from TransitionZero Solar Asset Mapper records (CC BY-NC 4.0, non-commercial reuse only). The open data files list that part separately.
The build-out by year
Show the figures as a table
| Year | Started operating | Solar PV | Concentrated solar | Onshore wind | Offshore wind | Hydropower | Geothermal | Bioenergy | Wind (type not stated) |
|---|---|---|---|---|---|---|---|---|---|
| 1994 | 68 MW | 0 | 0 | 0 | 0 | 68 MW | 0 | 0 | 0 |
| 2000 | 180 MW | 0 | 0 | 0 | 0 | 180 MW | 0 | 0 | 0 |
| 2018 | 6 MW | 6 MW | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 2023 | 80 MW | 0 | 0 | 0 | 0 | 80 MW | 0 | 0 | 0 |
| 2024 | 2.3 GW | 150 MW | 0 | 0 | 0 | 2,115 MW | 0 | 0 | 0 |
| 2025 | 4 MW | 4 MW | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Capacity of today's operating plants, by the year the plant started. Plants since retired are not in the data. 46 MW of operating capacity has no recorded start year and is left out of this chart. Earlier years and 2026 (a partial year) are in the data but outside the chart; the biggest year is 2024 with 2.3 GW.
Largest renewable plants in Tanzania
| # | Plant | Technology | Capacity | Status | Started |
|---|---|---|---|---|---|
| 1 | Julius Nyerere hydroelectric plant | Hydropower | 2.1 GW | Operating | 2024 |
| 2 | Kidatu hydroelectric plant | Hydropower | 200 MW | Operating | 1975 |
| 3 | Kihansi hydroelectric plant | Hydropower | 180 MW | Operating | 2000 |
| 4 | Kishapu solar farm | Solar PV | 150 MW | Operating | 2024 |
| 5 | Mtera hydroelectric plant | Hydropower | 80 MW | Operating | 1988 |
| 6 | Rusumo hydroelectric plant | Hydropower | 80 MW | Operating | 2023 |
| 7 | Pangani Falls hydroelectric plant | Hydropower | 68 MW | Operating | 1994 |
| 8 | TPC Sugar power station | Bioenergy | 18 MW | Operating | not recorded |
| 9 | Mtibwa Sugar power station | Bioenergy | 13 MW | Operating | not recorded |
| 10 | Sao Hill power station | Bioenergy | 6 MW | Operating | not recorded |
Largest in the pipeline
| # | Plant | Technology | Capacity | Status | Started |
|---|---|---|---|---|---|
| 1 | Tanzania solar farm | Solar PV | 600 MW | Announced | not recorded |
| 2 | Morogoro solar farm | Solar PV | 525 MW | Announced | not recorded |
| 3 | Zanzibar (Pougex Energy Proprietary) wind farm | Offshore wind | 450 MW | Announced | not recorded |
| 4 | Ruhudji hydroelectric plant | Hydropower | 358 MW | Announced | 2028 |
| 5 | Miombo Hewani wind farm | Onshore wind | 300 MW | Announced | not recorded |
Questions
How much renewable energy capacity does Tanzania have?
Tanzania has 2.9 GW of operating renewable capacity across 15 plants in the Global Energy Monitor data (solar, wind, hydropower, geothermal and bioenergy).
What is the biggest source of renewable capacity in Tanzania?
Hydropower, with 2.7 GW operating, which is 93% of Tanzania's operating renewable capacity in the data.
What share of Tanzania's power capacity is renewable?
78% of the operating capacity in this dataset (2.9 GW of 3.8 GW). This is a share of plant capacity listed by Global Energy Monitor, which tracks larger plants, not a share of the electricity actually generated or of national grid statistics.
How fast is Tanzania building renewables?
Operating plants that started from 2015 to 2025 total 2.4 GW, and the biggest single year in the data is 2024 with 2.3 GW. Plants with no recorded start year are not counted in the build-out by year.
What is the largest renewable plant in Tanzania?
Julius Nyerere hydroelectric plant, a hydropower plant of 2.1 GW, which started operating in 2024.
How much renewable capacity is being built or planned in Tanzania?
168 MW is under construction and 5.3 GW is announced or in pre-construction. Some announced projects will never be built.
Does Tanzania have offshore wind?
Yes: 0 MW operating, 0 MW under construction and 450 MW announced or in pre-construction.
Where does this data come from?
Global Energy Monitor, Global Integrated Power Tracker, September 2026 (Global Energy Monitor, Global Integrated Power Tracker, V2). Licensed CC BY 4.0, with some solar records CC BY-NC 4.0. Figures are as recorded by Global Energy Monitor and are not independently confirmed.