Renewable energy in Rwanda

Rwanda has 58 MW of operating renewable capacity in the data, across 4 plants. Hydropower is the largest source at 44 MW (76% of the total). That is 34% of the 169 MW of operating power capacity of all kinds that the same tracker lists for Rwanda (share of capacity in this dataset, not of national electricity generation). Plants that started operating from 2015 to 2025 add up to 14 MW, which is 24% of today's operating renewable capacity. A further 44 MW is under construction and 245 MW is announced or in pre-construction.

Operating
58 MW4 plants
Share of capacity in this dataset
34%of 169 MW operating, all kinds
Started 2015 to 2025
14 MWoperating plants
Pipeline
289 MW44 MW building, 245 MW announced

Capacity by technology

Renewable capacity in Rwanda by technology, operating and pipeline. Announced includes pre-construction.
TechnologyOperatingPlantsShareUnder constructionAnnounced
Solar PV14 MW324%0230 MW
Hydropower44 MW176%44 MW0
Bioenergy000.0%015 MW
All renewables58 MW4100%44 MW245 MW

Of the operating solar, 11 MW comes from TransitionZero Solar Asset Mapper records (CC BY-NC 4.0, non-commercial reuse only). The open data files list that part separately.

The build-out by year

0 MW10 MW20 MW19901995200020052010201520202025
Solar PVHydropower
Show the figures as a table
Operating renewable capacity in Rwanda by the year it started, 1990 to 2025
YearStarted operatingSolar PVConcentrated solarOnshore windOffshore windHydropowerGeothermalBioenergyWind (type not stated)
201712 MW12 MW0000000
20192 MW2 MW0000000

Capacity of today's operating plants, by the year the plant started. Plants since retired are not in the data. Earlier years and 2026 (a partial year) are in the data but outside the chart; the biggest year is 1989 with 44 MW.

Largest renewable plants in Rwanda

The ten largest operating renewable plants in Rwanda.
#PlantTechnologyCapacityStatusStarted
1Rusizi II hydroelectric plantHydropower44 MWOperating1989
2Rwamagana solar projectNCSolar PV8 MWOperating2017
3Nasho solar farmSolar PV3 MWOperating2017
4Bugesera District solar projectNCSolar PV2 MWOperating2019

Largest in the pipeline

The five largest renewable projects under construction or announced in Rwanda.
#PlantTechnologyCapacityStatusStarted
1Rwanda solar power projectSolar PV200 MWAnnouncednot recorded
2Nyabarongo II hydroelectric plantHydropower44 MWUnder construction2027
3Rwanda solar farmSolar PV30 MWAnnouncednot recorded
4Kavuma WtE power stationBioenergy15 MWAnnouncednot recorded

Questions

How much renewable energy capacity does Rwanda have?

Rwanda has 58 MW of operating renewable capacity across 4 plants in the Global Energy Monitor data (solar, wind, hydropower, geothermal and bioenergy).

What is the biggest source of renewable capacity in Rwanda?

Hydropower, with 44 MW operating, which is 76% of Rwanda's operating renewable capacity in the data.

What share of Rwanda's power capacity is renewable?

34% of the operating capacity in this dataset (58 MW of 169 MW). This is a share of plant capacity listed by Global Energy Monitor, which tracks larger plants, not a share of the electricity actually generated or of national grid statistics.

How fast is Rwanda building renewables?

Operating plants that started from 2015 to 2025 total 14 MW, and the biggest single year in the data is 1989 with 44 MW. Plants with no recorded start year are not counted in the build-out by year.

What is the largest renewable plant in Rwanda?

Rusizi II hydroelectric plant, a hydropower plant of 44 MW, which started operating in 1989.

How much renewable capacity is being built or planned in Rwanda?

44 MW is under construction and 245 MW is announced or in pre-construction. Some announced projects will never be built.

Where does this data come from?

Global Energy Monitor, Global Integrated Power Tracker, September 2026 (Global Energy Monitor, Global Integrated Power Tracker, V2). Licensed CC BY 4.0, with some solar records CC BY-NC 4.0. Figures are as recorded by Global Energy Monitor and are not independently confirmed.

Data as of September 2026 (Global Energy Monitor, Global Integrated Power Tracker, V2). Status counted: operating, under construction, and announced (including pre-construction). Retired, shelved, cancelled and mothballed plants are left out. Missing values are shown as missing. Method.