Renewable energy in El Salvador
El Salvador has 1.9 GW of operating renewable capacity in the data, across 82 plants. Solar PV is the largest source at 808 MW (42% of the total). That is 67% of the 2.9 GW of operating power capacity of all kinds that the same tracker lists for El Salvador (share of capacity in this dataset, not of national electricity generation). Plants that started operating from 2015 to 2025 add up to 1.0 GW, which is 54% of today's operating renewable capacity. A further 90 MW is under construction and 100 MW is announced or in pre-construction.
- Operating
- 1.9 GW82 plants
- Share of capacity in this dataset
- 67%of 2.9 GW operating, all kinds
- Started 2015 to 2025
- 1.0 GWoperating plants
- Pipeline
- 190 MW90 MW building, 100 MW announced
Capacity by technology
| Technology | Operating | Plants | Share | Under construction | Announced |
|---|---|---|---|---|---|
| Solar PV | 808 MW | 69 | 42% | 21 MW | 0 |
| Onshore wind | 54 MW | 1 | 2.8% | 0 | 100 MW |
| Hydropower | 599 MW | 4 | 31% | 0 | 0 |
| Geothermal | 219 MW | 3 | 11% | 69 MW | 0 |
| Bioenergy | 244 MW | 5 | 13% | 0 | 0 |
| All renewables | 1.9 GW | 82 | 100% | 90 MW | 100 MW |
Of the operating solar, 276 MW comes from TransitionZero Solar Asset Mapper records (CC BY-NC 4.0, non-commercial reuse only). The open data files list that part separately.
The build-out by year
Show the figures as a table
| Year | Started operating | Solar PV | Concentrated solar | Onshore wind | Offshore wind | Hydropower | Geothermal | Bioenergy | Wind (type not stated) |
|---|---|---|---|---|---|---|---|---|---|
| 1992 | 9 MW | 0 | 0 | 0 | 0 | 0 | 9 MW | 0 | 0 |
| 1999 | 56 MW | 0 | 0 | 0 | 0 | 0 | 56 MW | 0 | 0 |
| 2005 | 45 MW | 0 | 0 | 0 | 0 | 0 | 0 | 45 MW | 0 |
| 2007 | 45 MW | 0 | 0 | 0 | 0 | 0 | 45 MW | 0 | 0 |
| 2013 | 2 MW | 2 MW | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 2015 | 110 MW | 3 MW | 0 | 0 | 0 | 0 | 0 | 107 MW | 0 |
| 2016 | 48 MW | 1 MW | 0 | 0 | 0 | 0 | 0 | 47 MW | 0 |
| 2017 | 124 MW | 124 MW | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 2018 | 50 MW | 50 MW | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 2019 | 137 MW | 137 MW | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 2020 | 185 MW | 185 MW | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 2021 | 90 MW | 36 MW | 0 | 54 MW | 0 | 0 | 0 | 0 | 0 |
| 2022 | 31 MW | 31 MW | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 2023 | 164 MW | 91 MW | 0 | 0 | 0 | 67 MW | 6 MW | 0 | 0 |
| 2024 | 41 MW | 41 MW | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 2025 | 51 MW | 28 MW | 0 | 0 | 0 | 0 | 8 MW | 15 MW | 0 |
Capacity of today's operating plants, by the year the plant started. Plants since retired are not in the data. 109 MW of operating capacity has no recorded start year and is left out of this chart. Earlier years and 2026 (a partial year) are in the data but outside the chart; the biggest year is 1976 with 203 MW.
Largest renewable plants in El Salvador
| # | Plant | Technology | Capacity | Status | Started |
|---|---|---|---|---|---|
| 1 | 15 De Septiembre hydroelectric plant | Hydropower | 180 MW | Operating | 1983 |
| 2 | 5 De Noviembre hydroelectric plant | Hydropower | 179 MW | Operating | 1953 |
| 3 | Cerrón Grande hydroelectric plant | Hydropower | 173 MW | Operating | 1976 |
| 4 | Capella Solar Park | Solar PV | 140 MW | Operating | 2020 |
| 5 | Berlín geothermal power plant | Geothermal | 110 MW | Operating | 1992 |
| 6 | Ahuachapán geothermal power plant | Geothermal | 101 MW | Operating | 1975 |
| 7 | Providencia Solar Park | Solar PV | 100 MW | Operating | 2017 |
| 8 | 3 De Febrero hydroelectric plant | Hydropower | 67 MW | Operating | 2023 |
| 9 | Chaparrastique power station | Bioenergy | 62 MW | Operating | 2015 |
| 10 | Ingenio El Ángel power station | Bioenergy | 62 MW | Operating | 2016 |
Largest in the pipeline
| # | Plant | Technology | Capacity | Status | Started |
|---|---|---|---|---|---|
| 1 | Metapán wind farm | Onshore wind | 100 MW | Announced | not recorded |
| 2 | Chinameca geothermal power plant | Geothermal | 42 MW | Under construction | 2026 |
| 3 | San Vicente geothermal power plant | Geothermal | 27 MW | Under construction | 2026 |
| 4 | Holcim Cement Plant solar farm | Solar PV | 21 MW | Under construction | not recorded |
Questions
How much renewable energy capacity does El Salvador have?
El Salvador has 1.9 GW of operating renewable capacity across 82 plants in the Global Energy Monitor data (solar, wind, hydropower, geothermal and bioenergy).
What is the biggest source of renewable capacity in El Salvador?
Solar PV, with 808 MW operating, which is 42% of El Salvador's operating renewable capacity in the data.
What share of El Salvador's power capacity is renewable?
67% of the operating capacity in this dataset (1.9 GW of 2.9 GW). This is a share of plant capacity listed by Global Energy Monitor, which tracks larger plants, not a share of the electricity actually generated or of national grid statistics.
How fast is El Salvador building renewables?
Operating plants that started from 2015 to 2025 total 1.0 GW, and the biggest single year in the data is 1976 with 203 MW. Plants with no recorded start year are not counted in the build-out by year.
What is the largest renewable plant in El Salvador?
15 De Septiembre hydroelectric plant, a hydropower plant of 180 MW, which started operating in 1983.
How much renewable capacity is being built or planned in El Salvador?
90 MW is under construction and 100 MW is announced or in pre-construction. Some announced projects will never be built.
Where does this data come from?
Global Energy Monitor, Global Integrated Power Tracker, September 2026 (Global Energy Monitor, Global Integrated Power Tracker, V2). Licensed CC BY 4.0, with some solar records CC BY-NC 4.0. Figures are as recorded by Global Energy Monitor and are not independently confirmed.
Related countries
Data as of September 2026 (Global Energy Monitor, Global Integrated Power Tracker, V2). Status counted: operating, under construction, and announced (including pre-construction). Retired, shelved, cancelled and mothballed plants are left out. Missing values are shown as missing. Method.