Renewable energy in Côte d'Ivoire

Côte d'Ivoire has 1.1 GW of operating renewable capacity in the data, across 8 plants. Hydropower is the largest source at 966 MW (92% of the total). That is 39% of the 2.7 GW of operating power capacity of all kinds that the same tracker lists for Côte d'Ivoire (share of capacity in this dataset, not of national electricity generation). Plants that started operating from 2015 to 2025 add up to 425 MW, which is 41% of today's operating renewable capacity. A further 268 MW is under construction and 1.3 GW is announced or in pre-construction.

Operating
1.1 GW8 plants
Share of capacity in this dataset
39%of 2.7 GW operating, all kinds
Started 2015 to 2025
425 MWoperating plants
Pipeline
1.6 GW268 MW building, 1.3 GW announced

Capacity by technology

Renewable capacity in Côte d'Ivoire by technology, operating and pipeline. Announced includes pre-construction.
TechnologyOperatingPlantsShareUnder constructionAnnounced
Solar PV38 MW13.6%224 MW783 MW
Hydropower966 MW692%44 MW402 MW
Bioenergy46 MW14.4%0101 MW
All renewables1.1 GW8100%268 MW1.3 GW

The build-out by year

0 MW250 MW500 MW19901995200020052010201520202025
Solar PVHydropowerBioenergy
Show the figures as a table
Operating renewable capacity in Côte d'Ivoire by the year it started, 1990 to 2025
YearStarted operatingSolar PVConcentrated solarOnshore windOffshore windHydropowerGeothermalBioenergyWind (type not stated)
2017275 MW0000275 MW000
202238 MW38 MW0000000
2024112 MW0000112 MW000

Capacity of today's operating plants, by the year the plant started. Plants since retired are not in the data. Earlier years and 2026 (a partial year) are in the data but outside the chart; the biggest year is 2017 with 275 MW.

Largest renewable plants in Côte d'Ivoire

The ten largest operating renewable plants in Côte d'Ivoire.
#PlantTechnologyCapacityStatusStarted
1Soubre hydroelectric plantHydropower275 MWOperating2017
2Taabo hydroelectric plantHydropower210 MWOperating1979
3Kossou hydroelectric plantHydropower174 MWOperating1972
4Buyo hydroelectric plantHydropower165 MWOperating1980
5Gribo-Popoli hydroelectric plantHydropower112 MWOperating2024
6Biokala power stationBioenergy46 MWOperating2026
7Boundiali solar farmSolar PV38 MWOperating2022
8Ayame II hydroelectric plantHydropower30 MWOperating1965

Largest in the pipeline

The five largest renewable projects under construction or announced in Côte d'Ivoire.
#PlantTechnologyCapacityStatusStarted
1Boutoubre hydroelectric plantHydropower156 MWAnnouncednot recorded
2Louga 1 hydroelectric plantHydropower126 MWAnnouncednot recorded
3Louga 2 hydroelectric plantHydropower120 MWAnnounced2027
4Korhogo solar farmSolar PV116 MWAnnounced2026
5Dabakala solar farmSolar PV100 MWAnnouncednot recorded

Questions

How much renewable energy capacity does Côte d'Ivoire have?

Côte d'Ivoire has 1.1 GW of operating renewable capacity across 8 plants in the Global Energy Monitor data (solar, wind, hydropower, geothermal and bioenergy).

What is the biggest source of renewable capacity in Côte d'Ivoire?

Hydropower, with 966 MW operating, which is 92% of Côte d'Ivoire's operating renewable capacity in the data.

What share of Côte d'Ivoire's power capacity is renewable?

39% of the operating capacity in this dataset (1.1 GW of 2.7 GW). This is a share of plant capacity listed by Global Energy Monitor, which tracks larger plants, not a share of the electricity actually generated or of national grid statistics.

How fast is Côte d'Ivoire building renewables?

Operating plants that started from 2015 to 2025 total 425 MW, and the biggest single year in the data is 2017 with 275 MW. Plants with no recorded start year are not counted in the build-out by year.

What is the largest renewable plant in Côte d'Ivoire?

Soubre hydroelectric plant, a hydropower plant of 275 MW, which started operating in 2017.

How much renewable capacity is being built or planned in Côte d'Ivoire?

268 MW is under construction and 1.3 GW is announced or in pre-construction. Some announced projects will never be built.

Where does this data come from?

Global Energy Monitor, Global Integrated Power Tracker, September 2026 (Global Energy Monitor, Global Integrated Power Tracker, V2). Licensed CC BY 4.0, with some solar records CC BY-NC 4.0. Figures are as recorded by Global Energy Monitor and are not independently confirmed.

Data as of September 2026 (Global Energy Monitor, Global Integrated Power Tracker, V2). Status counted: operating, under construction, and announced (including pre-construction). Retired, shelved, cancelled and mothballed plants are left out. Missing values are shown as missing. Method.