Renewable energy in Algeria

Algeria has 657 MW of operating renewable capacity in the data, across 39 plants. Solar PV is the largest source at 431 MW (66% of the total). That is 2.3% of the 28.4 GW of operating power capacity of all kinds that the same tracker lists for Algeria (share of capacity in this dataset, not of national electricity generation). Plants that started operating from 2015 to 2025 add up to 431 MW, which is 66% of today's operating renewable capacity. A further 2.5 GW is under construction and 1.9 GW is announced or in pre-construction.

Operating
657 MW39 plants
Share of capacity in this dataset
2.3%of 28.4 GW operating, all kinds
Started 2015 to 2025
431 MWoperating plants
Pipeline
4.4 GW2.5 GW building, 1.9 GW announced

Capacity by technology

Renewable capacity in Algeria by technology, operating and pipeline. Announced includes pre-construction.
TechnologyOperatingPlantsShareUnder constructionAnnounced
Solar PV431 MW3466%2.5 GW1.9 GW
Concentrated solar20 MW13.0%00
Onshore wind10 MW11.5%00
Hydropower196 MW330%00
All renewables657 MW39100%2.5 GW1.9 GW

Of the operating solar, 136 MW comes from TransitionZero Solar Asset Mapper records (CC BY-NC 4.0, non-commercial reuse only). The open data files list that part separately.

The build-out by year

0 MW100 MW200 MW19901995200020052010201520202025
Solar PVConcentrated solarOnshore windHydropower
Show the figures as a table
Operating renewable capacity in Algeria by the year it started, 1990 to 2025
YearStarted operatingSolar PVConcentrated solarOnshore windOffshore windHydropowerGeothermalBioenergyWind (type not stated)
201120 MW020 MW000000
201410 MW0010 MW00000
201520 MW20 MW0000000
2016128 MW128 MW0000000
2017199 MW199 MW0000000
201810 MW10 MW0000000
202117 MW17 MW0000000
20223 MW3 MW0000000
202324 MW24 MW0000000
202429 MW29 MW0000000

Capacity of today's operating plants, by the year the plant started. Plants since retired are not in the data. Earlier years and 2026 (a partial year) are in the data but outside the chart; the biggest year is 2017 with 199 MW.

Largest renewable plants in Algeria

The ten largest operating renewable plants in Algeria.
#PlantTechnologyCapacityStatusStarted
1Mansouria hydroelectric plantHydropower100 MWOperating1963
2Darguinah hydroelectric plantHydropower72 MWOperating1952
3El Kheneg solar farmSolar PV60 MWOperating2016
4Ain El Ibel SolarSolar PV53 MWOperating2016
5Ain Skhouna SolarSolar PV30 MWOperating2016
6HPC Ouargla solar farmSolar PV30 MWOperating2017
7Ighil Emda hydroelectric plantHydropower24 MWOperating1952
8El-Abiodh solar farmSolar PV23 MWOperating2016
9Adrar Solar PlantSolar PV20 MWOperating2015
10Ain El Mehl SolarSolar PV20 MWOperating2017

Largest in the pipeline

The five largest renewable projects under construction or announced in Algeria.
#PlantTechnologyCapacityStatusStarted
1Hassi Delaa solar farmSolar PV362 MWAnnounced2028
2Laghouat (Özgün İnşaat) solar farmSolar PV362 MWUnder construction2026
3Foulia solar farmSolar PV300 MWUnder construction2026
4El Oued solar farmSolar PV280 MWUnder construction2026
5Tamacine solar farmSolar PV250 MWAnnounced2028

Questions

How much renewable energy capacity does Algeria have?

Algeria has 657 MW of operating renewable capacity across 39 plants in the Global Energy Monitor data (solar, wind, hydropower, geothermal and bioenergy).

What is the biggest source of renewable capacity in Algeria?

Solar PV, with 431 MW operating, which is 66% of Algeria's operating renewable capacity in the data.

What share of Algeria's power capacity is renewable?

2.3% of the operating capacity in this dataset (657 MW of 28.4 GW). This is a share of plant capacity listed by Global Energy Monitor, which tracks larger plants, not a share of the electricity actually generated or of national grid statistics.

How fast is Algeria building renewables?

Operating plants that started from 2015 to 2025 total 431 MW, and the biggest single year in the data is 2017 with 199 MW. Plants with no recorded start year are not counted in the build-out by year.

What is the largest renewable plant in Algeria?

Mansouria hydroelectric plant, a hydropower plant of 100 MW, which started operating in 1963.

How much renewable capacity is being built or planned in Algeria?

2.5 GW is under construction and 1.9 GW is announced or in pre-construction. Some announced projects will never be built.

Where does this data come from?

Global Energy Monitor, Global Integrated Power Tracker, September 2026 (Global Energy Monitor, Global Integrated Power Tracker, V2). Licensed CC BY 4.0, with some solar records CC BY-NC 4.0. Figures are as recorded by Global Energy Monitor and are not independently confirmed.

Data as of September 2026 (Global Energy Monitor, Global Integrated Power Tracker, V2). Status counted: operating, under construction, and announced (including pre-construction). Retired, shelved, cancelled and mothballed plants are left out. Missing values are shown as missing. Method.