Renewable energy in Guinea
Guinea has 815 MW of operating renewable capacity in the data, across 4 plants. Hydropower is the largest source at 815 MW (100% of the total). That is 68% of the 1.2 GW of operating power capacity of all kinds that the same tracker lists for Guinea (share of capacity in this dataset, not of national electricity generation). Plants that started operating from 2015 to 2025 add up to 690 MW, which is 85% of today's operating renewable capacity. A further 300 MW is under construction and 1.3 GW is announced or in pre-construction.
- Operating
- 815 MW4 plants
- Share of capacity in this dataset
- 68%of 1.2 GW operating, all kinds
- Started 2015 to 2025
- 690 MWoperating plants
- Pipeline
- 1.6 GW300 MW building, 1.3 GW announced
Capacity by technology
| Technology | Operating | Plants | Share | Under construction | Announced |
|---|---|---|---|---|---|
| Solar PV | 0 | 0 | 0.0% | 0 | 672 MW |
| Hydropower | 815 MW | 4 | 100% | 300 MW | 586 MW |
| All renewables | 815 MW | 4 | 100% | 300 MW | 1.3 GW |
The build-out by year
Show the figures as a table
| Year | Started operating | Solar PV | Concentrated solar | Onshore wind | Offshore wind | Hydropower | Geothermal | Bioenergy | Wind (type not stated) |
|---|---|---|---|---|---|---|---|---|---|
| 2000 | 80 MW | 0 | 0 | 0 | 0 | 80 MW | 0 | 0 | 0 |
| 2015 | 240 MW | 0 | 0 | 0 | 0 | 240 MW | 0 | 0 | 0 |
| 2020 | 450 MW | 0 | 0 | 0 | 0 | 450 MW | 0 | 0 | 0 |
Capacity of today's operating plants, by the year the plant started. Plants since retired are not in the data. 45 MW of operating capacity has no recorded start year and is left out of this chart. Earlier years and 2026 (a partial year) are in the data but outside the chart; the biggest year is 2020 with 450 MW.
Largest renewable plants in Guinea
| # | Plant | Technology | Capacity | Status | Started |
|---|---|---|---|---|---|
| 1 | Souapiti hydroelectric plant | Hydropower | 450 MW | Operating | 2020 |
| 2 | Kaleta hydroelectric plant | Hydropower | 240 MW | Operating | 2015 |
| 3 | Garafiri hydroelectric plant | Hydropower | 80 MW | Operating | 2000 |
| 4 | Boke hydroelectric plant | Hydropower | 45 MW | Operating | not recorded |
Largest in the pipeline
| # | Plant | Technology | Capacity | Status | Started |
|---|---|---|---|---|---|
| 1 | Guinea-Conakry solar project | Solar PV | 500 MW | Announced | not recorded |
| 2 | Amaria hydroelectric plant | Hydropower | 300 MW | Under construction | not recorded |
| 3 | Koukoutamba hydroelectric plant | Hydropower | 294 MW | Announced | not recorded |
| 4 | Kogbèdou hydroelectric plant | Hydropower | 102 MW | Announced | not recorded |
| 5 | Morisanako hydroelectric plant | Hydropower | 100 MW | Announced | not recorded |
Questions
How much renewable energy capacity does Guinea have?
Guinea has 815 MW of operating renewable capacity across 4 plants in the Global Energy Monitor data (solar, wind, hydropower, geothermal and bioenergy).
What is the biggest source of renewable capacity in Guinea?
Hydropower, with 815 MW operating, which is 100% of Guinea's operating renewable capacity in the data.
What share of Guinea's power capacity is renewable?
68% of the operating capacity in this dataset (815 MW of 1.2 GW). This is a share of plant capacity listed by Global Energy Monitor, which tracks larger plants, not a share of the electricity actually generated or of national grid statistics.
How fast is Guinea building renewables?
Operating plants that started from 2015 to 2025 total 690 MW, and the biggest single year in the data is 2020 with 450 MW. Plants with no recorded start year are not counted in the build-out by year.
What is the largest renewable plant in Guinea?
Souapiti hydroelectric plant, a hydropower plant of 450 MW, which started operating in 2020.
How much renewable capacity is being built or planned in Guinea?
300 MW is under construction and 1.3 GW is announced or in pre-construction. Some announced projects will never be built.
Where does this data come from?
Global Energy Monitor, Global Integrated Power Tracker, September 2026 (Global Energy Monitor, Global Integrated Power Tracker, V2). Licensed CC BY 4.0, with some solar records CC BY-NC 4.0. Figures are as recorded by Global Energy Monitor and are not independently confirmed.
Related countries
Data as of September 2026 (Global Energy Monitor, Global Integrated Power Tracker, V2). Status counted: operating, under construction, and announced (including pre-construction). Retired, shelved, cancelled and mothballed plants are left out. Missing values are shown as missing. Method.