Renewable energy in Guinea

Guinea has 815 MW of operating renewable capacity in the data, across 4 plants. Hydropower is the largest source at 815 MW (100% of the total). That is 68% of the 1.2 GW of operating power capacity of all kinds that the same tracker lists for Guinea (share of capacity in this dataset, not of national electricity generation). Plants that started operating from 2015 to 2025 add up to 690 MW, which is 85% of today's operating renewable capacity. A further 300 MW is under construction and 1.3 GW is announced or in pre-construction.

Operating
815 MW4 plants
Share of capacity in this dataset
68%of 1.2 GW operating, all kinds
Started 2015 to 2025
690 MWoperating plants
Pipeline
1.6 GW300 MW building, 1.3 GW announced

Capacity by technology

Renewable capacity in Guinea by technology, operating and pipeline. Announced includes pre-construction.
TechnologyOperatingPlantsShareUnder constructionAnnounced
Solar PV000.0%0672 MW
Hydropower815 MW4100%300 MW586 MW
All renewables815 MW4100%300 MW1.3 GW

The build-out by year

0 MW250 MW500 MW19901995200020052010201520202025
Hydropower
Show the figures as a table
Operating renewable capacity in Guinea by the year it started, 1990 to 2025
YearStarted operatingSolar PVConcentrated solarOnshore windOffshore windHydropowerGeothermalBioenergyWind (type not stated)
200080 MW000080 MW000
2015240 MW0000240 MW000
2020450 MW0000450 MW000

Capacity of today's operating plants, by the year the plant started. Plants since retired are not in the data. 45 MW of operating capacity has no recorded start year and is left out of this chart. Earlier years and 2026 (a partial year) are in the data but outside the chart; the biggest year is 2020 with 450 MW.

Largest renewable plants in Guinea

The ten largest operating renewable plants in Guinea.
#PlantTechnologyCapacityStatusStarted
1Souapiti hydroelectric plantHydropower450 MWOperating2020
2Kaleta hydroelectric plantHydropower240 MWOperating2015
3Garafiri hydroelectric plantHydropower80 MWOperating2000
4Boke hydroelectric plantHydropower45 MWOperatingnot recorded

Largest in the pipeline

The five largest renewable projects under construction or announced in Guinea.
#PlantTechnologyCapacityStatusStarted
1Guinea-Conakry solar projectSolar PV500 MWAnnouncednot recorded
2Amaria hydroelectric plantHydropower300 MWUnder constructionnot recorded
3Koukoutamba hydroelectric plantHydropower294 MWAnnouncednot recorded
4Kogbèdou hydroelectric plantHydropower102 MWAnnouncednot recorded
5Morisanako hydroelectric plantHydropower100 MWAnnouncednot recorded

Questions

How much renewable energy capacity does Guinea have?

Guinea has 815 MW of operating renewable capacity across 4 plants in the Global Energy Monitor data (solar, wind, hydropower, geothermal and bioenergy).

What is the biggest source of renewable capacity in Guinea?

Hydropower, with 815 MW operating, which is 100% of Guinea's operating renewable capacity in the data.

What share of Guinea's power capacity is renewable?

68% of the operating capacity in this dataset (815 MW of 1.2 GW). This is a share of plant capacity listed by Global Energy Monitor, which tracks larger plants, not a share of the electricity actually generated or of national grid statistics.

How fast is Guinea building renewables?

Operating plants that started from 2015 to 2025 total 690 MW, and the biggest single year in the data is 2020 with 450 MW. Plants with no recorded start year are not counted in the build-out by year.

What is the largest renewable plant in Guinea?

Souapiti hydroelectric plant, a hydropower plant of 450 MW, which started operating in 2020.

How much renewable capacity is being built or planned in Guinea?

300 MW is under construction and 1.3 GW is announced or in pre-construction. Some announced projects will never be built.

Where does this data come from?

Global Energy Monitor, Global Integrated Power Tracker, September 2026 (Global Energy Monitor, Global Integrated Power Tracker, V2). Licensed CC BY 4.0, with some solar records CC BY-NC 4.0. Figures are as recorded by Global Energy Monitor and are not independently confirmed.

Data as of September 2026 (Global Energy Monitor, Global Integrated Power Tracker, V2). Status counted: operating, under construction, and announced (including pre-construction). Retired, shelved, cancelled and mothballed plants are left out. Missing values are shown as missing. Method.