Renewable energy in Barbados

Barbados has 26 MW of operating renewable capacity in the data, across 10 plants. Solar PV is the largest source at 25 MW (96% of the total). That is 12% of the 209 MW of operating power capacity of all kinds that the same tracker lists for Barbados (share of capacity in this dataset, not of national electricity generation). Plants that started operating from 2015 to 2025 add up to 26 MW, which is 100% of today's operating renewable capacity. A further 50 MW is under construction and 130 MW is announced or in pre-construction.

Operating
26 MW10 plants
Share of capacity in this dataset
12%of 209 MW operating, all kinds
Started 2015 to 2025
26 MWoperating plants
Pipeline
180 MW50 MW building, 130 MW announced

Capacity by technology

Renewable capacity in Barbados by technology, operating and pipeline. Announced includes pre-construction.
TechnologyOperatingPlantsShareUnder constructionAnnounced
Solar PV25 MW996%0130 MW
Onshore wind1 MW13.9%50 MW0
All renewables26 MW10100%50 MW130 MW

Of the operating solar, 14 MW comes from TransitionZero Solar Asset Mapper records (CC BY-NC 4.0, non-commercial reuse only). The open data files list that part separately.

The build-out by year

0 MW5 MW10 MW19901995200020052010201520202025
Solar PVOnshore wind
Show the figures as a table
Operating renewable capacity in Barbados by the year it started, 1990 to 2025
YearStarted operatingSolar PVConcentrated solarOnshore windOffshore windHydropowerGeothermalBioenergyWind (type not stated)
201610 MW10 MW0000000
20183 MW3 MW0000000
20202 MW2 MW0000000
20214 MW4 MW0000000
20222 MW2 MW0000000
20235 MW4 MW01 MW00000

Capacity of today's operating plants, by the year the plant started. Plants since retired are not in the data. Earlier years and 2026 (a partial year) are in the data but outside the chart; the biggest year is 2016 with 10 MW.

Largest renewable plants in Barbados

The ten largest operating renewable plants in Barbados.
#PlantTechnologyCapacityStatusStarted
1Saint Lucy solar farmSolar PV10 MWOperating2016
2Saint Thomas solar projectNCSolar PV3 MWOperating2018
3Saint Philip solar project IINCSolar PV3 MWOperating2021
4Saint Peter solar projectNCSolar PV2 MWOperating2020
5Saint Lucy solar projectNCSolar PV2 MWOperating2022
6Saint George solar project INCSolar PV1 MWOperating2023
7Saint John solar projectNCSolar PV1 MWOperating2021
8Saint John solar project INCSolar PV1 MWOperating2023
9Saint George solar projectSolar PV1 MWOperating2023
10Ashford Plantation wind farmOnshore wind1 MWOperating2023

Largest in the pipeline

The five largest renewable projects under construction or announced in Barbados.
#PlantTechnologyCapacityStatusStarted
1Community Solar GardensSolar PV60 MWAnnouncednot recorded
2Renewstable Barbados solar farmSolar PV50 MWAnnounced2028
3Lamberts Wind Farm ProjectOnshore wind50 MWUnder constructionnot recorded
4Saint Philip solar farmSolar PV10 MWAnnouncednot recorded
5Waterford Plantation solar farmSolar PV10 MWAnnouncednot recorded

Questions

How much renewable energy capacity does Barbados have?

Barbados has 26 MW of operating renewable capacity across 10 plants in the Global Energy Monitor data (solar, wind, hydropower, geothermal and bioenergy).

What is the biggest source of renewable capacity in Barbados?

Solar PV, with 25 MW operating, which is 96% of Barbados's operating renewable capacity in the data.

What share of Barbados's power capacity is renewable?

12% of the operating capacity in this dataset (26 MW of 209 MW). This is a share of plant capacity listed by Global Energy Monitor, which tracks larger plants, not a share of the electricity actually generated or of national grid statistics.

How fast is Barbados building renewables?

Operating plants that started from 2015 to 2025 total 26 MW, and the biggest single year in the data is 2016 with 10 MW. Plants with no recorded start year are not counted in the build-out by year.

What is the largest renewable plant in Barbados?

Saint Lucy solar farm, a solar pv plant of 10 MW, which started operating in 2016.

How much renewable capacity is being built or planned in Barbados?

50 MW is under construction and 130 MW is announced or in pre-construction. Some announced projects will never be built.

Where does this data come from?

Global Energy Monitor, Global Integrated Power Tracker, September 2026 (Global Energy Monitor, Global Integrated Power Tracker, V2). Licensed CC BY 4.0, with some solar records CC BY-NC 4.0. Figures are as recorded by Global Energy Monitor and are not independently confirmed.

Data as of September 2026 (Global Energy Monitor, Global Integrated Power Tracker, V2). Status counted: operating, under construction, and announced (including pre-construction). Retired, shelved, cancelled and mothballed plants are left out. Missing values are shown as missing. Method.