Renewable energy in Argentina

Argentina has 19.8 GW of operating renewable capacity in the data, across 147 plants. Hydropower is the largest source at 11.6 GW (59% of the total). That is 43% of the 46.0 GW of operating power capacity of all kinds that the same tracker lists for Argentina (share of capacity in this dataset, not of national electricity generation). Plants that started operating from 2015 to 2025 add up to 7.6 GW, which is 38% of today's operating renewable capacity. A further 1.2 GW is under construction and 18.3 GW is announced or in pre-construction.

Operating
19.8 GW147 plants
Share of capacity in this dataset
43%of 46.0 GW operating, all kinds
Started 2015 to 2025
7.6 GWoperating plants
Pipeline
19.5 GW1.2 GW building, 18.3 GW announced

Capacity by technology

Renewable capacity in Argentina by technology, operating and pipeline. Announced includes pre-construction.
TechnologyOperatingPlantsShareUnder constructionAnnounced
Solar PV3.0 GW6515%455 MW4.9 GW
Onshore wind5.0 GW4625%355 MW3.9 GW
Hydropower11.6 GW2859%360 MW5.1 GW
Geothermal000.0%090 MW
Bioenergy254 MW81.3%00
Wind (type not stated)000.0%04.3 GW
All renewables19.8 GW147100%1.2 GW18.3 GW

Of the operating solar, 52 MW comes from TransitionZero Solar Asset Mapper records (CC BY-NC 4.0, non-commercial reuse only). The open data files list that part separately.

The build-out by year

0 MW2.5 GW5.0 GW19901995200020052010201520202025
Solar PVOnshore windHydropowerBioenergy
Show the figures as a table
Operating renewable capacity in Argentina by the year it started, 1990 to 2025
YearStarted operatingSolar PVConcentrated solarOnshore windOffshore windHydropowerGeothermalBioenergyWind (type not stated)
1990120 MW0000120 MW000
19931.4 GW00001,424 MW000
19943.1 GW00003,100 MW000
199660 MW000060 MW000
199730 MW000030 MW000
1999285 MW0000285 MW000
200018 MW0018 MW00000
2002150 MW0000150 MW000
200351 MW000051 MW000
2009213 MW0050 MW0125 MW038 MW0
201052 MW8 MW0000044 MW0
201146 MW006 MW00040 MW0
2012106 MW23 MW083 MW00000
201350 MW0050 MW00000
201665 MW000065 MW000
2017135 MW00125 MW00010 MW0
2018737 MW243 MW0494 MW00000
20191.2 GW249 MW0902 MW00000
20201.4 GW330 MW01,059 MW00058 MW0
20211.0 GW365 MW0642 MW00000
202260 MW60 MW0000000
2023721 MW304 MW0418 MW00000
2024889 MW327 MW0538 MW00024 MW0
20251.3 GW1,013 MW0289 MW00040 MW0

Capacity of today's operating plants, by the year the plant started. Plants since retired are not in the data. 347 MW of operating capacity has no recorded start year and is left out of this chart. Earlier years and 2026 (a partial year) are in the data but outside the chart; the biggest year is 1994 with 3.1 GW.

Largest renewable plants in Argentina

The ten largest operating renewable plants in Argentina.
#PlantTechnologyCapacityStatusStarted
1Yacyretá hydroelectric plantHydropower3.1 GWOperating1994
2Salto Grande hydroelectric plant (Argentina-Uruguay)Hydropower1.9 GWOperating1979
3Piedra Del Aguila hydroelectric plantHydropower1.4 GWOperating1993
4Chocón hydroelectric plantHydropower1.2 GWOperating1972
5Alicura hydroelectric plantHydropower1.0 GWOperating1984
6Planicie Banderita hydroelectric plantHydropower486 MWOperating1972
7Futaleufú hydroelectric plantHydropower472 MWOperating1978
8Pampa Energia wind farmOnshore wind327 MWOperating2019
9Cauchari Solar Power ComplexSolar PV315 MWOperating2020
10Loma Blanca wind farmOnshore wind304 MWOperating2020

Largest in the pipeline

The five largest renewable projects under construction or announced in Argentina.
#PlantTechnologyCapacityStatusStarted
1Gaucho wind farmWind (type not stated)4.2 GWAnnounced2026
2Corpus Christi hydroelectric plantHydropower2.9 GWAnnounced2034
3Jáchal solar farmSolar PV1.0 GWAnnouncednot recorded
4Chihuido 1 hydroelectric plantHydropower637 MWAnnounced2029
5Panambi hydroelectric plantHydropower576 MWAnnouncednot recorded

Questions

How much renewable energy capacity does Argentina have?

Argentina has 19.8 GW of operating renewable capacity across 147 plants in the Global Energy Monitor data (solar, wind, hydropower, geothermal and bioenergy).

What is the biggest source of renewable capacity in Argentina?

Hydropower, with 11.6 GW operating, which is 59% of Argentina's operating renewable capacity in the data.

What share of Argentina's power capacity is renewable?

43% of the operating capacity in this dataset (19.8 GW of 46.0 GW). This is a share of plant capacity listed by Global Energy Monitor, which tracks larger plants, not a share of the electricity actually generated or of national grid statistics.

How fast is Argentina building renewables?

Operating plants that started from 2015 to 2025 total 7.6 GW, and the biggest single year in the data is 1994 with 3.1 GW. Plants with no recorded start year are not counted in the build-out by year.

What is the largest renewable plant in Argentina?

Yacyretá hydroelectric plant, a hydropower plant of 3.1 GW, which started operating in 1994.

How much renewable capacity is being built or planned in Argentina?

1.2 GW is under construction and 18.3 GW is announced or in pre-construction. Some announced projects will never be built.

Where does this data come from?

Global Energy Monitor, Global Integrated Power Tracker, September 2026 (Global Energy Monitor, Global Integrated Power Tracker, V2). Licensed CC BY 4.0, with some solar records CC BY-NC 4.0. Figures are as recorded by Global Energy Monitor and are not independently confirmed.

Data as of September 2026 (Global Energy Monitor, Global Integrated Power Tracker, V2). Status counted: operating, under construction, and announced (including pre-construction). Retired, shelved, cancelled and mothballed plants are left out. Missing values are shown as missing. Method.