Renewable energy in Uzbekistan

Uzbekistan has 6.0 GW of operating renewable capacity in the data, across 56 plants. Solar PV is the largest source at 2.5 GW (42% of the total). That is 25% of the 24.0 GW of operating power capacity of all kinds that the same tracker lists for Uzbekistan (share of capacity in this dataset, not of national electricity generation). Plants that started operating from 2015 to 2025 add up to 4.2 GW, which is 69% of today's operating renewable capacity. A further 1.3 GW is under construction and 17.6 GW is announced or in pre-construction.

Operating
6.0 GW56 plants
Share of capacity in this dataset
25%of 24.0 GW operating, all kinds
Started 2015 to 2025
4.2 GWoperating plants
Pipeline
18.9 GW1.3 GW building, 17.6 GW announced

Capacity by technology

Renewable capacity in Uzbekistan by technology, operating and pipeline. Announced includes pre-construction.
TechnologyOperatingPlantsShareUnder constructionAnnounced
Solar PV2.5 GW3842%757 MW3.9 GW
Onshore wind1.6 GW427%20 MW13.4 GW
Hydropower1.9 GW1432%490 MW200 MW
Bioenergy000.0%20 MW92 MW
All renewables6.0 GW56100%1.3 GW17.6 GW

Of the operating solar, 71 MW comes from TransitionZero Solar Asset Mapper records (CC BY-NC 4.0, non-commercial reuse only). The open data files list that part separately.

The build-out by year

0 MW2.5 GW5.0 GW19901995200020052010201520202025
Solar PVOnshore windHydropower
Show the figures as a table
Operating renewable capacity in Uzbekistan by the year it started, 1990 to 2025
YearStarted operatingSolar PVConcentrated solarOnshore windOffshore windHydropowerGeothermalBioenergyWind (type not stated)
201095 MW000095 MW000
20175 MW5 MW0000000
2021175 MW100 MW00075 MW000
2022101 MW101 MW0000000
2023202 MW27 MW000175 MW000
20242.2 GW1,243 MW01,000 MW00000
20251.4 GW848 MW0600 MW00000

Capacity of today's operating plants, by the year the plant started. Plants since retired are not in the data. Earlier years and 2026 (a partial year) are in the data but outside the chart; the biggest year is 2024 with 2.2 GW.

Largest renewable plants in Uzbekistan

The ten largest operating renewable plants in Uzbekistan.
#PlantTechnologyCapacityStatusStarted
1Charvak hydroelectric plantHydropower666 MWOperating1977
2Karaulbazar solar farmSolar PV500 MWOperating2024
3Nishan solar farmSolar PV500 MWOperating2024
4Bash wind farmOnshore wind500 MWOperating2024
5Dzhankeldy wind farmOnshore wind500 MWOperating2024
6Zarafshan wind farmOnshore wind500 MWOperating2025
7Buka solar farmSolar PV263 MWOperating2025
8Nur-Bukhara solar farmSolar PV250 MWOperating2025
9Jizzakh solar farmSolar PV220 MWOperating2025
10Samarkand (Masdar) solar farmSolar PV220 MWOperating2024

Largest in the pipeline

The five largest renewable projects under construction or announced in Uzbekistan.
#PlantTechnologyCapacityStatusStarted
1Aral wind farmOnshore wind5.0 GWAnnouncednot recorded
2Kungrad (ACWA Power) wind farmOnshore wind2.0 GWAnnounced2027
3Sazagan solar farmSolar PV1.0 GWAnnouncednot recorded
4AMEA Karakalpakstan wind farmOnshore wind1.0 GWAnnouncednot recorded
5Kungrad (Sany Renewable) wind farmOnshore wind1.0 GWAnnouncednot recorded

Questions

How much renewable energy capacity does Uzbekistan have?

Uzbekistan has 6.0 GW of operating renewable capacity across 56 plants in the Global Energy Monitor data (solar, wind, hydropower, geothermal and bioenergy).

What is the biggest source of renewable capacity in Uzbekistan?

Solar PV, with 2.5 GW operating, which is 42% of Uzbekistan's operating renewable capacity in the data.

What share of Uzbekistan's power capacity is renewable?

25% of the operating capacity in this dataset (6.0 GW of 24.0 GW). This is a share of plant capacity listed by Global Energy Monitor, which tracks larger plants, not a share of the electricity actually generated or of national grid statistics.

How fast is Uzbekistan building renewables?

Operating plants that started from 2015 to 2025 total 4.2 GW, and the biggest single year in the data is 2024 with 2.2 GW. Plants with no recorded start year are not counted in the build-out by year.

What is the largest renewable plant in Uzbekistan?

Charvak hydroelectric plant, a hydropower plant of 666 MW, which started operating in 1977.

How much renewable capacity is being built or planned in Uzbekistan?

1.3 GW is under construction and 17.6 GW is announced or in pre-construction. Some announced projects will never be built.

Where does this data come from?

Global Energy Monitor, Global Integrated Power Tracker, September 2026 (Global Energy Monitor, Global Integrated Power Tracker, V2). Licensed CC BY 4.0, with some solar records CC BY-NC 4.0. Figures are as recorded by Global Energy Monitor and are not independently confirmed.