Renewable energy in India

India has 187 GW of operating renewable capacity in the data, across 4,721 plants. Solar PV is the largest source at 99.1 GW (53% of the total). That is 39% of the 485 GW of operating power capacity of all kinds that the same tracker lists for India (share of capacity in this dataset, not of national electricity generation). Plants that started operating from 2015 to 2025 add up to 119 GW, which is 64% of today's operating renewable capacity. A further 143 GW is under construction and 152 GW is announced or in pre-construction.

Operating
187 GW4,721 plants
Share of capacity in this dataset
39%of 485 GW operating, all kinds
Started 2015 to 2025
119 GWoperating plants
Pipeline
295 GW143 GW building, 152 GW announced

Capacity by technology

Renewable capacity in India by technology, operating and pipeline. Announced includes pre-construction.
TechnologyOperatingPlantsShareUnder constructionAnnounced
Solar PV99.1 GW3,68353%104 GW89.4 GW
Concentrated solar225 MW30.1%050 MW
Onshore wind38.9 GW62021%25.7 GW17.3 GW
Offshore wind000.0%05.0 GW
Hydropower43.8 GW21423%13.2 GW37.5 GW
Bioenergy4.8 GW2002.6%44 MW150 MW
Wind (type not stated)10 MW1<0.1%667 MW2.4 GW
All renewables187 GW4,721100%143 GW152 GW

Of the operating solar, 15.6 GW comes from TransitionZero Solar Asset Mapper records (CC BY-NC 4.0, non-commercial reuse only). The open data files list that part separately.

The build-out by year

0 MW10.0 GW20.0 GW19901995200020052010201520202025
Solar PVConcentrated solarOnshore windHydropowerBioenergy
Show the figures as a table
Operating renewable capacity in India by the year it started, 1990 to 2025
YearStarted operatingSolar PVConcentrated solarOnshore windOffshore windHydropowerGeothermalBioenergyWind (type not stated)
199095 MW0015 MW080 MW000
1991378 MW0000378 MW000
1992336 MW0000318 MW018 MW0
199365 MW00000065 MW0
1994725 MW0000660 MW065 MW0
199566 MW0010 MW050 MW06 MW0
1996649 MW00120 MW0514 MW015 MW0
1997458 MW0000405 MW053 MW0
1998232 MW0000188 MW044 MW0
19991.7 GW00001,695 MW000
2000936 MW0000930 MW06 MW0
2001547 MW0059 MW0448 MW040 MW0
2002479 MW0000435 MW044 MW0
20032.2 GW00002,100 MW0124 MW0
20041.8 GW0049 MW01,540 MW0189 MW0
2005630 MW00105 MW0453 MW072 MW0
20061.9 GW00108 MW01,616 MW0128 MW0
20071.3 GW00152 MW01,010 MW0169 MW0
20082.3 GW00536 MW01,498 MW0252 MW0
2009512 MW00367 MW000145 MW0
20101.6 GW00552 MW0812 MW0193 MW0
20112.3 GW98 MW0604 MW01,271 MW0311 MW0
20122.8 GW529 MW125 MW1,342 MW0375 MW0436 MW0
20133.0 GW736 MW50 MW1,466 MW0557 MW0169 MW0
20142.8 GW722 MW50 MW952 MW0932 MW097 MW0
20155.1 GW1,265 MW01,802 MW01,916 MW0101 MW0
20166.3 GW3,391 MW02,299 MW0475 MW0153 MW0
201716.5 GW12,102 MW02,654 MW01,679 MW050 MW0
201811.8 GW9,004 MW02,234 MW0440 MW076 MW0
20198.3 GW6,099 MW02,127 MW00030 MW0
20205.0 GW3,632 MW0548 MW0810 MW000
20219.1 GW7,372 MW01,445 MW0213 MW038 MW0
202215.7 GW13,529 MW01,864 MW0300 MW000
20238.1 GW5,361 MW02,614 MW060 MW055 MW0
202417.3 GW15,476 MW01,757 MW0100 MW012 MW0
202515.7 GW13,215 MW01,275 MW01,140 MW024 MW0

Capacity of today's operating plants, by the year the plant started. Plants since retired are not in the data. 20.1 GW of operating capacity has no recorded start year and is left out of this chart. Earlier years and 2026 (a partial year) are in the data but outside the chart; the biggest year is 2024 with 17.3 GW.

Largest renewable plants in India

The ten largest operating renewable plants in India.
#PlantTechnologyCapacityStatusStarted
1Khavda (Adani) IV solar farmSolar PV2.0 GWOperatingnot recorded
2Fatehgarh (Adani) solar farmSolar PV1.5 GWOperating2025
3Nathpa Jhakri hydroelectric plantHydropower1.5 GWOperating2003
4Bhinajpura solar farmSolar PV1.3 GWOperating2025
5Teesta-III hydroelectric plantHydropower1.2 GWOperating2017
6Karcham Wangtoo hydroelectric plantHydropower1.0 GWOperating2011
7Sharavathy hydroelectric plantHydropower1.0 GWOperating1965
8Bhadla III Solar ParkSolar PV1.0 GWOperating2018
9Khavda (Adani) solar farmSolar PV1.0 GWOperating2024
10Rajasthan (SJVN) III solar farmSolar PV1.0 GWOperating2025

Largest in the pipeline

The five largest renewable projects under construction or announced in India.
#PlantTechnologyCapacityStatusStarted
1Siang Upper hydroelectric plantHydropower10.0 GWAnnouncednot recorded
2Ladakh Solar ParkSolar PV9.0 GWAnnounced2029
3Pancheshwar hydroelectric plantHydropower6.5 GWAnnounced2034
4Jaisalmer Manufacturing (Adani Group) solar farmSolar PV4.9 GWUnder construction2026
5Kutch (NTPC) Solar ParkSolar PV4.8 GWUnder construction2026

Questions

How much renewable energy capacity does India have?

India has 187 GW of operating renewable capacity across 4,721 plants in the Global Energy Monitor data (solar, wind, hydropower, geothermal and bioenergy).

What is the biggest source of renewable capacity in India?

Solar PV, with 99.1 GW operating, which is 53% of India's operating renewable capacity in the data.

What share of India's power capacity is renewable?

39% of the operating capacity in this dataset (187 GW of 485 GW). This is a share of plant capacity listed by Global Energy Monitor, which tracks larger plants, not a share of the electricity actually generated or of national grid statistics.

How fast is India building renewables?

Operating plants that started from 2015 to 2025 total 119 GW, and the biggest single year in the data is 2024 with 17.3 GW. Plants with no recorded start year are not counted in the build-out by year.

What is the largest renewable plant in India?

Khavda (Adani) IV solar farm, a solar pv plant of 2.0 GW.

How much renewable capacity is being built or planned in India?

143 GW is under construction and 152 GW is announced or in pre-construction. Some announced projects will never be built.

Does India have offshore wind?

Yes: 0 MW operating, 0 MW under construction and 5.0 GW announced or in pre-construction.

Where does this data come from?

Global Energy Monitor, Global Integrated Power Tracker, September 2026 (Global Energy Monitor, Global Integrated Power Tracker, V2). Licensed CC BY 4.0, with some solar records CC BY-NC 4.0. Figures are as recorded by Global Energy Monitor and are not independently confirmed.

Data as of September 2026 (Global Energy Monitor, Global Integrated Power Tracker, V2). Status counted: operating, under construction, and announced (including pre-construction). Retired, shelved, cancelled and mothballed plants are left out. Missing values are shown as missing. Method.