Renewable energy in Botswana

Botswana has 134 MW of operating renewable capacity in the data, across 7 plants. Solar PV is the largest source at 134 MW (100% of the total). That is 14% of the 936 MW of operating power capacity of all kinds that the same tracker lists for Botswana (share of capacity in this dataset, not of national electricity generation). Plants that started operating from 2015 to 2025 add up to 74 MW, which is 55% of today's operating renewable capacity. A further 0 MW is under construction and 4.0 GW is announced or in pre-construction.

Operating
134 MW7 plants
Share of capacity in this dataset
14%of 936 MW operating, all kinds
Started 2015 to 2025
74 MWoperating plants
Pipeline
4.0 GW0 MW building, 4.0 GW announced

Capacity by technology

Renewable capacity in Botswana by technology, operating and pipeline. Announced includes pre-construction.
TechnologyOperatingPlantsShareUnder constructionAnnounced
Solar PV134 MW7100%02.5 GW
Concentrated solar000.0%01.3 GW
Onshore wind000.0%0150 MW
All renewables134 MW7100%0 MW4.0 GW

Of the operating solar, 14 MW comes from TransitionZero Solar Asset Mapper records (CC BY-NC 4.0, non-commercial reuse only). The open data files list that part separately.

The build-out by year

0 MW50 MW100 MW19901995200020052010201520202025
Solar PV
Show the figures as a table
Operating renewable capacity in Botswana by the year it started, 1990 to 2025
YearStarted operatingSolar PVConcentrated solarOnshore windOffshore windHydropowerGeothermalBioenergyWind (type not stated)
20172 MW2 MW0000000
20222 MW2 MW0000000
202310 MW10 MW0000000
202560 MW60 MW0000000

Capacity of today's operating plants, by the year the plant started. Plants since retired are not in the data. Earlier years and 2026 (a partial year) are in the data but outside the chart; the biggest year is 2025 with 60 MW.

Largest renewable plants in Botswana

The ten largest operating renewable plants in Botswana.
#PlantTechnologyCapacityStatusStarted
1Mmadinare Solar ComplexSolar PV120 MWOperating2025
2Central District solar projectNCSolar PV7 MWOperating2023
3North-West District solar projectNCSolar PV2 MWOperating2023
4Gaborone solar projectNCSolar PV2 MWOperating2017
5Lephalale Local Municipality Waterberg District Municipality solar projectNCSolar PV1 MWOperating2022
6Gaborone solar project IINCSolar PV1 MWOperating2022
7Gaborone solar project INCSolar PV1 MWOperating2023

Largest in the pipeline

The five largest renewable projects under construction or announced in Botswana.
#PlantTechnologyCapacityStatusStarted
1Mega Solar Initiative solar farm (Botswana)Solar PV1.4 GWAnnouncednot recorded
2Mega Solar Initiative solar farm (Botswana)Concentrated solar1.1 GWAnnouncednot recorded
3Leupane Energy Hub solar farmSolar PV500 MWAnnouncednot recorded
4Botswana CSP I solar farmConcentrated solar200 MWAnnounced2027
5Jwaneng solar farmSolar PV100 MWAnnounced2026

Questions

How much renewable energy capacity does Botswana have?

Botswana has 134 MW of operating renewable capacity across 7 plants in the Global Energy Monitor data (solar, wind, hydropower, geothermal and bioenergy).

What is the biggest source of renewable capacity in Botswana?

Solar PV, with 134 MW operating, which is 100% of Botswana's operating renewable capacity in the data.

What share of Botswana's power capacity is renewable?

14% of the operating capacity in this dataset (134 MW of 936 MW). This is a share of plant capacity listed by Global Energy Monitor, which tracks larger plants, not a share of the electricity actually generated or of national grid statistics.

How fast is Botswana building renewables?

Operating plants that started from 2015 to 2025 total 74 MW, and the biggest single year in the data is 2025 with 60 MW. Plants with no recorded start year are not counted in the build-out by year.

What is the largest renewable plant in Botswana?

Mmadinare Solar Complex, a solar pv plant of 120 MW, which started operating in 2025.

How much renewable capacity is being built or planned in Botswana?

0 MW is under construction and 4.0 GW is announced or in pre-construction. Some announced projects will never be built.

Where does this data come from?

Global Energy Monitor, Global Integrated Power Tracker, September 2026 (Global Energy Monitor, Global Integrated Power Tracker, V2). Licensed CC BY 4.0, with some solar records CC BY-NC 4.0. Figures are as recorded by Global Energy Monitor and are not independently confirmed.

Data as of September 2026 (Global Energy Monitor, Global Integrated Power Tracker, V2). Status counted: operating, under construction, and announced (including pre-construction). Retired, shelved, cancelled and mothballed plants are left out. Missing values are shown as missing. Method.