Renewable energy in Azerbaijan

Azerbaijan has 1.6 GW of operating renewable capacity in the data, across 23 plants. Hydropower is the largest source at 1.2 GW (76% of the total). That is 18% of the 8.7 GW of operating power capacity of all kinds that the same tracker lists for Azerbaijan (share of capacity in this dataset, not of national electricity generation). Plants that started operating from 2015 to 2025 add up to 536 MW, which is 34% of today's operating renewable capacity. A further 481 MW is under construction and 4.3 GW is announced or in pre-construction.

Operating
1.6 GW23 plants
Share of capacity in this dataset
18%of 8.7 GW operating, all kinds
Started 2015 to 2025
536 MWoperating plants
Pipeline
4.7 GW481 MW building, 4.3 GW announced

Capacity by technology

Renewable capacity in Azerbaijan by technology, operating and pipeline. Announced includes pre-construction.
TechnologyOperatingPlantsShareUnder constructionAnnounced
Solar PV304 MW1419%445 MW1.5 GW
Onshore wind50 MW13.1%0721 MW
Offshore wind000.0%02.0 GW
Hydropower1.2 GW776%36 MW0
Bioenergy37 MW12.3%00
All renewables1.6 GW23100%481 MW4.3 GW

Of the operating solar, 54 MW comes from TransitionZero Solar Asset Mapper records (CC BY-NC 4.0, non-commercial reuse only). The open data files list that part separately.

The build-out by year

0 MW250 MW500 MW19901995200020052010201520202025
Solar PVOnshore windHydropowerBioenergy
Show the figures as a table
Operating renewable capacity in Azerbaijan by the year it started, 1990 to 2025
YearStarted operatingSolar PVConcentrated solarOnshore windOffshore windHydropowerGeothermalBioenergyWind (type not stated)
2000150 MW0000150 MW000
201237 MW00000037 MW0
201425 MW000025 MW000
201520 MW20 MW0000000
20178 MW8 MW0000000
201868 MW18 MW050 MW00000
20198 MW8 MW0000000
202113 MW13 MW0000000
2023230 MW230 MW0000000
2024187 MW5 MW000182 MW000
20253 MW3 MW0000000

Capacity of today's operating plants, by the year the plant started. Plants since retired are not in the data. Earlier years and 2026 (a partial year) are in the data but outside the chart; the biggest year is 1954 with 424 MW.

Largest renewable plants in Azerbaijan

The ten largest operating renewable plants in Azerbaijan.
#PlantTechnologyCapacityStatusStarted
1Mingechevir hydroelectric plantHydropower424 MWOperating1954
2Shamkir hydroelectric plantHydropower380 MWOperating1983
3Garadagh Solar PV PlantSolar PV230 MWOperating2023
4Yenikend hydroelectric plantHydropower150 MWOperating2000
5Khudafarin (Khoda Afarin) hydroelectric plantHydropower102 MWOperating2024
6Gyz Galasy hydroelectric plantHydropower80 MWOperating2024
7Yeni Yashma wind farmOnshore wind50 MWOperating2018
8Sarsang hydroelectric plantHydropower50 MWOperating1976
9Balakhani power stationBioenergy37 MWOperating2012
10Shamkirchay hydroelectric plantHydropower25 MWOperating2014

Largest in the pipeline

The five largest renewable projects under construction or announced in Azerbaijan.
#PlantTechnologyCapacityStatusStarted
1Azerbaijan Caspian Sea wind farmOffshore wind2.0 GWAnnouncednot recorded
2Nakhchivan (A-Z Czech Engineering) solar farmSolar PV500 MWAnnouncednot recorded
3Bilasuvar solar farmSolar PV445 MWUnder constructionnot recorded
4Neftchala solar farmSolar PV315 MWAnnouncednot recorded
5Khizi-Absheron wind farmOnshore wind241 MWAnnounced2026

Questions

How much renewable energy capacity does Azerbaijan have?

Azerbaijan has 1.6 GW of operating renewable capacity across 23 plants in the Global Energy Monitor data (solar, wind, hydropower, geothermal and bioenergy).

What is the biggest source of renewable capacity in Azerbaijan?

Hydropower, with 1.2 GW operating, which is 76% of Azerbaijan's operating renewable capacity in the data.

What share of Azerbaijan's power capacity is renewable?

18% of the operating capacity in this dataset (1.6 GW of 8.7 GW). This is a share of plant capacity listed by Global Energy Monitor, which tracks larger plants, not a share of the electricity actually generated or of national grid statistics.

How fast is Azerbaijan building renewables?

Operating plants that started from 2015 to 2025 total 536 MW, and the biggest single year in the data is 1954 with 424 MW. Plants with no recorded start year are not counted in the build-out by year.

What is the largest renewable plant in Azerbaijan?

Mingechevir hydroelectric plant, a hydropower plant of 424 MW, which started operating in 1954.

How much renewable capacity is being built or planned in Azerbaijan?

481 MW is under construction and 4.3 GW is announced or in pre-construction. Some announced projects will never be built.

Does Azerbaijan have offshore wind?

Yes: 0 MW operating, 0 MW under construction and 2.0 GW announced or in pre-construction.

Where does this data come from?

Global Energy Monitor, Global Integrated Power Tracker, September 2026 (Global Energy Monitor, Global Integrated Power Tracker, V2). Licensed CC BY 4.0, with some solar records CC BY-NC 4.0. Figures are as recorded by Global Energy Monitor and are not independently confirmed.

Data as of September 2026 (Global Energy Monitor, Global Integrated Power Tracker, V2). Status counted: operating, under construction, and announced (including pre-construction). Retired, shelved, cancelled and mothballed plants are left out. Missing values are shown as missing. Method.